Check/Generalize the tracking for single chamber

Added by Sanghwa Park 2 months ago. Updated 29 days ago.

Status:
New
Priority:
Normal
Assignee:
Start date:
02/12/2026
Due date:
% Done:

50%

Estimated time:

Files

sng_chamber_dc.png (40.8 KB) sng_chamber_dc.png Sanghwa Park, 03/26/2026 09:02 AM
Actions #1

Updated by Sanghwa Park 29 days ago

Single chamber DC reconstruction test using R-SIDIS data. It uses the stubs from the chamber as tracks (no linking stubs between two chambers). Optics reconstruction needs a bit more work, but close to submit a PR.

Actions #2

Updated by Sanghwa Park 29 days ago

  • % Done changed from 0 to 50