openGlobal Run Plan
20%
Description
Detailed Run Plan with Physics Production settings, NPS-Calorimeter Calibration settings, HMS optics settings.
Overleaf document:
https://www.overleaf.com/read/jfmdzdwctkrf
Updated by Alexandre Camsonne 9 months ago
Need commissionning part feedback
20 days kinematic - split ?
LD2 switching ? every day
Updated by Alexandre Camsonne 9 months ago
Start commisionning at 3 pass
switch to 5 pass
Thresholds on calorimeter ? Pion MIP : 300 MeV don't want to go below
Updated by Alexandre Camsonne 9 months ago
Add the two cluster threshold ( if implemented ) could try 200 MeV for 2 clusters ?
Threshold over 2 GeV might be ok. Sum of all energy trigger ?
Updated by Alexandre Camsonne 9 months ago
add low current run at beginning and record with no thresholds
Updated by Alexandre Camsonne 9 months ago
Take with 2 different beam current
Difficult to analyse several trigger
Short HMS only runs for efficiency checks
Need to analyzie inclusive rates
Peter can give numbers to Zheng