| 1 | 1 | Jacob Murphy | h1. Summer 2022 Run Plans and Run Sheets  | 
|---|---|---|---|
| 2 | |||
| 3 | * Blank Run Sheets  | 
||
| 4 | ** New Configuration Sheet attachment:runsheet_pion21.tgif.ps  | 
||
| 5 | ** Continuing Configuration Sheet attachment:runsheet_pion21.tgif.ps  | 
||
| 6 | |||
| 7 | * Run Plan Spread Sheet attachment:pion_loweps_runplan_21dec20.ods  | 
||
| 8 | |||
| 9 | * JLab Beam Schedule attachment:20210316_JLab_ExpSch.pdf attachment:20211004_JLab_ExpSch.pdf attachment:20211122_JLab_ExpSch.pdf  | 
||
| 10 | * Beam pipe requirements attachment:beampipe_req.pdf  | 
||
| 11 | * SHMS small angle test 21-Jun-09 attachment:angle_test_21jun09.pdf  | 
||
| 12 | |||
| 13 | 2 | Jacob Murphy | h2. 10.6 GeV Beam  | 
| 14 | 1 | Jacob Murphy | |
| 15 | * Run Plan attachment:runplan_9p2gev.pdf  | 
||
| 16 | * Scanned run plan (with shift worker and RC notes) attachment:runplan_9p2gev_scan.pdf  | 
||
| 17 | 3 | Jacob Murphy | * 10.6 GeV Run list attachment:runlist_pionLT_2021_Eb_9p173.csv  | 
| 18 | * 10.6 GeV Run list (formatted) attachment:runlist_pionLT_2021_Eb_9p173.ods attachment:runlist_pionLT_2021_Eb_9p173.pdf  | 
||
| 19 | 1 | Jacob Murphy | |
| 20 | 2 | Jacob Murphy | h3. 10.6 GeV Run sheets  | 
| 21 | 1 | Jacob Murphy | |
| 22 | ** Calibrations #1 (Heep-Coin, Sieve1) attachment:runsheets_9p2gev_calib1.pdf  | 
||
| 23 | ** Physics Q2=1.60, W=3.08 attachment:runsheets_9p2gev_q21p60_w3p08.pdf  | 
||
| 24 | ** Calibrations #2 (Heep-Singles, Lumi, fADC Deadtime) attachment:runsheets_9p2gev_calib2.pdf  | 
||
| 25 | ** Physics Q2=6.00, W=3.19 LEFT attachment:runsheets_9p2gev_q26p00_w3p19_left.pdf  | 
||
| 26 | ** Physics Q2=6.00, W=3.19 CENTER attachment:runsheets_9p2gev_q26p00_w3p19_center.pdf  | 
||
| 27 | ** Physics Q2=8.50, W=2.79 attachment:runsheets_9p2gev_q28p50_w2p79.pdf  | 
||
| 28 | |||
| 29 | 2 | Jacob Murphy | h2. 8.5 GeV Beam  | 
| 30 | 1 | Jacob Murphy | |
| 31 | * Run Plan attachment:runplan_9p9gev.pdf  | 
||
| 32 | * Scanned run plan (with shift worker and RC notes) attachment:runplan_9p9gev_scan.pdf  | 
||
| 33 | 3 | Jacob Murphy | * 8.5 GeV Run list attachment:runlist_pionLT_2021_Eb_9p876.csv  | 
| 34 | * 8.5 GeV Run list (formatted) attachment:runlist_pionLT_2021_Eb_9p876.ods attachment:runlist_pionLT_2021_Eb_9p876.pdf  | 
||
| 35 | 1 | Jacob Murphy | |
| 36 | 2 | Jacob Murphy | h3. 8.5 GeV Run sheets  | 
| 37 | 1 | Jacob Murphy | |
| 38 | ** Calibrations (Heep-Singles, Coin) attachment:runsheets_9p9gev_calib.pdf  | 
||
| 39 | ** Physics Q2=1.60, W=3.08 attachment:runsheets_9p9gev_q21p60_w3p08.pdf  | 
||
| 40 | ** Physics Q2=3.85, W=3.07 attachment:runsheets_9p9gev_q23p85_w3p07.pdf  | 
||
| 41 | ** Physics Q2=5.00, W=2.95 attachment:runsheets_9p9gev_q25p00_w2p95.pdf  | 
||
| 42 | ** Physics Q2=6.00, W=3.19 attachment:runsheets_9p9gev_q26p00_w3p19.pdf  | 
||
| 43 | |||
| 44 | 2 | Jacob Murphy | h2. 6.4 GeV Beam  | 
| 45 | 1 | Jacob Murphy | |
| 46 | * Run Plan Part 1 (December) attachment:runplan_8p0gev-1.pdf  | 
||
| 47 | * Run Plan Part 2 (Jan/Feb) attachment:runplan_8p0gev-2.pdf  | 
||
| 48 | * Scanned run plan (December) (with shift worker and RC notes) attachment:runplan_8p0gev-1_scan.pdf  | 
||
| 49 | * Scanned run plan (Jan/Feb) (with shift worker and RC notes) attachment:runplan_8p0gev-2_scan.pdf  | 
||
| 50 | * Special EDTM study w/ Cosmics attachment:Runplan_EDTM_21dec01.pdf  | 
||
| 51 | 3 | Jacob Murphy | * 6.4 GeV Run list (December) attachment:runlist_pionLT_2021_Eb_7p937_Part1.csv  | 
| 52 | * 6.4 GeV Run list (Jan/Feb) attachment:runlist_pionLT_2021_Eb_7p937_Part2.csv  | 
||
| 53 | * 6.4 GeV Run list (formatted--December) attachment:runlist_pionLT_2021_Eb_7p937_Part1.ods attachment:runlist_pionLT_2021_Eb_7p937_Part1.pdf  | 
||
| 54 | * 6.4 GeV Run list (formatted--Jan/Feb) attachment:runlist_pionLT_2021_Eb_7p937_Part2.ods attachment:runlist_pionLT_2021_Eb_7p937_Part2.pdf  | 
||
| 55 | 1 | Jacob Murphy | |
| 56 | 2 | Jacob Murphy | h3. 6.4 GeV Run sheets  | 
| 57 | 1 | Jacob Murphy | |
| 58 | ** Physics #1 pi- (December) attachment:runsheets_8p0gev-1_piminus.pdf  | 
||
| 59 | ** Calibrations #1 (Heep-Singles, Lumi, EDTM) attachment:runsheets_8p0gev_calib1.pdf  | 
||
| 60 | ** Special EDTM study w/ Cosmics attachment:runsheets_EDTM_21dec01.pdf  | 
||
| 61 | ** Physics #2 pi+ (December) attachment:runsheets_8p0gev-2_piplus.pdf  | 
||
| 62 | ** Physics #3A pi+ (Jan/Feb) attachment:runsheets_8p0gev-3A_piplus.pdf  | 
||
| 63 | ** Physics #3B pi+ (Jan/Feb) attachment:runsheets_8p0gev-3B_piplus.pdf  | 
||
| 64 | ** Calibrations #2 (Heep-Coin, fADC Deadtime, Lumi) attachment:runsheets_8p0gev_calib2.pdf  | 
||
| 65 | ** Physics #4 pi- (Feb) attachment:runsheets_8p0gev-4_piminus.pdf  |