h1. Summer 2022 Run Plans and Run Sheets 

 * Blank Run Sheets 
 ** New Configuration Sheet attachment:runsheet_pion21.tgif.ps 
 ** Continuing Configuration Sheet attachment:runsheet2_pion21.tgif.ps 
 ** To print, use command lpr -# n runsheet.tgif.ps from the command line, where n is the number of copies desired  
 ** To view, use command gv from command line 
 * Run Plan Spread Sheet attachment:pion_hieps_runplan_22aug11.ods 
 * JLab Beam Schedule attachment:20220610_JLab_ExpSch.pdf attachment:20220724_JLab_ExpSch.pdf 

 h2. 10.6 GeV Beam 

 * Run Plan attachment:10_549_GeV_Runplan.pdf  
 * Scanned run plan (with shift worker and RC notes) attachment:runplan_10p6gev_scan.pdf 
 * 10.6 GeV Run list attachment:runlist_pionLT_2022_Eb_10p549.csv 
 * 10.6 GeV Run list (formatted) attachment: 

 h3. 10.6 GeV Run sheets 

 ** Optics #1 (Sieve1,TriggerCheck) attachment:runsheets_10p6gev_Optics1.pdf 
 ** Optics/HeepSing attachment:runsheets_10p6gev_OpticsHeep.pdf 
 ** Special Heep (HMS 6 GeV/c) attachment:runsheets_10p6gev_Heep6HMS.pdf 
 ** Heep Coin attachment:runsheets_10p6gev_HeepCoin.pdf 
 ** Physics Q2=2.45, W=3.20 attachment:runsheets_10p6gev_q22p45_w3p20.pdf 
 ** Physics Q2=2.73, W=2.63 attachment:runsheets_10p6gev_q22p73_w2p63.pdf 
 ** Physics Q2=3.85, W=2.02 attachment:runsheets_10p6gev_q23p85_w2p02.pdf 
 ** Physics Q2=3.85, W=2.62 attachment:runsheets_10p6gev_q23p85_w2p62.pdf attachment:runsheets_10p6gev_q23p85_w2p62_minus.pdf 
 ** Physics Q2=3.85, W=3.07 attachment:runsheets_10p6gev_q23p85_w3p07.pdf attachment:runsheets_10p6gev_q23p85_w3p07_minus.pdf 
 ** Physics Q2=5.00, W=2.95 attachment:runsheets_10p6gev_q25p00_w2p95.pdf 
 ** Physics Q2=6.00, W=2.40 attachment:runsheets_10p6gev_q26p00_w2p40-1.pdf attachment:runsheets_10p6gev_q26p00_w2p40-2.pdf attachment:runsheets_10p6gev_q26p00_w2p40_minus.pdf 
 ** Physics Q2=6.00, W=3.19 attachment:runsheets_10p6gev_q26p00_w3p19-1.pdf attachment:runsheets_10p6gev_q26p00_w3p19-2.pdf 
 ** Physics Q2=8.50, W=2.79 attachment:runsheets_10p6gev_q28p50_w2p79.pdf 

 h2. 8.5 GeV Beam 

 * Run Plan attachment:runplan_8p487GeV_v11.pdf 
 * Run Plan addendum for HeeP Singles and Optics:8_GeV_Runplan_Adendum Singles/Optics:8_GeV_Runplan_Adendum.pdf 
 * Scanned run plan (with shift worker and RC notes) attachment: 
 * 8.5 GeV Run list attachment: 
 * 8.5 GeV Run list (formatted) attachment: 

 h3. 8.5 GeV Run sheets 

 ** Calibrations (Heep-Singles, Coin) attachment:runsheets_9p9gev_calib.pdf 
 ** Physics Q2=1.60, W=3.08 attachment:runsheets_9p9gev_q21p60_w3p08.pdf 
 ** Physics Q2=3.85, W=3.07 attachment:runsheets_9p9gev_q23p85_w3p07.pdf 
 ** Physics Q2=5.00, W=2.95 attachment:runsheets_9p9gev_q25p00_w2p95.pdf 
 ** Physics Q2=6.00, W=3.19 attachment:runsheets_9p9gev_q26p00_w3p19.pdf 

 h2. 6.4 GeV Beam 

 * Run Plan Part attachment:2022Runplan6p4GeV.pdf 
 * Scanned run plan (with shift worker and RC notes) attachment:runplan_6p4gev_scan.pdf 
 * 6.4 GeV Run list attachment:runlist_pionLT_2021_Eb_6p4.csv 
 * 6.4 GeV Run list (formatted) attachment:runlist_pionLT_2021_Eb_6p4.ods attachment:runlist_pionLT_2021_Eb_6p4.pdf 

 h3. 6.4 GeV Run sheets 

 ** Physics #1 pi- (December) attachment:runsheets_8p0gev-1_piminus.pdf 
 ** Calibrations #1 (Heep-Singles, Lumi, EDTM) attachment:runsheets_8p0gev_calib1.pdf 
 ** Special EDTM study w/ Cosmics attachment:runsheets_EDTM_21dec01.pdf 
 ** Physics #2 pi+ (December) attachment:runsheets_8p0gev-2_piplus.pdf 
 ** Physics #3A pi+ (Jan/Feb) attachment:runsheets_8p0gev-3A_piplus.pdf 
 ** Physics #3B pi+ (Jan/Feb) attachment:runsheets_8p0gev-3B_piplus.pdf 
 ** Calibrations #2 (Heep-Coin, fADC Deadtime, Lumi) attachment:runsheets_8p0gev_calib2.pdf 
 ** Physics #4 pi- (Feb) attachment:runsheets_8p0gev-4_piminus.pdf