h1. May 7th 2026 

 *Updates 
 * May 25th going in - 2 weeks 
 ** 1 UVA 2 Hall B GEM, Cerenkov, Ecal, Sctinillatorrs, 3 Hall B uRWell, uRwell UVA , uRGroove -  
 **  

 *Run plan 
 ** what we need to do at beginning 
 ** what needs to be measured 


  

 **GEM 
 *** need set up cosmics setup 
 *** Can we test all MPGDs at same time ?  
 *** test GEM one by one 
 *** trigger : cosmics trigger  
 *** add small scintillator for effciency 
 *** plateau scan ? 
 *** make stand to take cosmics with most or all of MPGDs - use actual stand and put veritcal maybe 
 *** all APVs, MPDs , need one slot backplane only for uRGroove and uRWell 
 *** need config with both ADC and GEM 

 **PMTs 
 ***put 1 scinitillor - can take data, need to figure latency. 
 *** copied simple decoder but need to adjust windows 

 **Software 
 *** start with simple decoder 
 *** all SBS online installed in container with Penguin and Podd 

 **Counting house 
 *** setup CODA on solidpc2 
 *** basic config with TI in Hall C 
 *** prepare FADC and GEM