Actions
Task #1002
openTask #997: Hodoscope Work at ESB
Task #1000: ASSY 6
ASSY 6 Optic Fibers
Start date:
04/08/2024
Due date:
04/26/2024 (about 8 months late)
% Done:
100%
Estimated time:
Description
Status of the fibers and issues
Updated by Carlos Ayerbe Gayoso 8 months ago
- Subject changed from Optic Fibers to ASSY 6 Optic Fibers
Updated by Florian Hauenstein 8 months ago
- % Done changed from 0 to 50
Current status:
11 bars have old fibers removed.
10 bars have fiber installed along the bar.
The 6 bars which are at the moment not on the main frame have the fiber connected to the bar with tape. 3 of them were tested for good light connection to the bar.
No fiber has RTV sealing yet.
Next:
Add remaining fibers to bars, check for fiber connection and seal with RTV.
Updated by Florian Hauenstein 8 months ago
- % Done changed from 50 to 90
All fibers are installed and sealed with RTV. Light connection tested for all bars.
Missing: Lightleak check around RTV and application of more seals if necessary.
Updated by Florian Hauenstein 8 months ago
- % Done changed from 90 to 100
All done. Also checked for light leaks.
Actions