Project

General

Profile

Actions

Task #1002

open

Task #997: Hodoscope Work at ESB

Task #1000: ASSY 6

ASSY 6 Optic Fibers

Added by Carlos Ayerbe Gayoso 14 days ago. Updated 8 days ago.

Status:
In Progress
Priority:
Normal
Start date:
04/08/2024
Due date:
04/26/2024 (3 days late)
% Done:

90%

Estimated time:

Description

Status of the fibers and issues

Actions #1

Updated by Carlos Ayerbe Gayoso 14 days ago

  • Subject changed from Optic Fibers to ASSY 6 Optic Fibers
Actions #2

Updated by Florian Hauenstein 14 days ago

  • % Done changed from 0 to 50

Current status:
11 bars have old fibers removed.
10 bars have fiber installed along the bar.
The 6 bars which are at the moment not on the main frame have the fiber connected to the bar with tape. 3 of them were tested for good light connection to the bar.
No fiber has RTV sealing yet.

Next:
Add remaining fibers to bars, check for fiber connection and seal with RTV.

Actions #3

Updated by Florian Hauenstein 8 days ago

  • % Done changed from 50 to 90

All fibers are installed and sealed with RTV. Light connection tested for all bars.

Missing: Lightleak check around RTV and application of more seals if necessary.

Actions

Also available in: Atom PDF