Task #1229

open

PiFi Construction

Added by Sho Nagao 3 months ago. Updated 15 days ago.

Status:
New
Priority:
Normal
Assignee:
Start date:
03/05/2026
Due date:
03/31/2027 (Due in about 10 months)
% Done:

0%

Estimated time:
(Total: 0.00 h)

Subtasks 14 (14 open0 closed)

Task #1111: Vacuum PortNewSho Nagao03/05/202608/31/2026

Actions
Task #1226: Vacuum Port DesignNew03/05/202606/12/2026

Actions
Task #1227: Vacuum Port FabricationNew06/15/202607/31/2026

Actions
Task #1228: Clear Fiber CutNewSho Nagao06/19/202607/31/2026

Actions
Task #1256: Clear Fiber AssemblingNew08/01/202608/31/2026

Actions
Task #1230: OLS FiberNew03/05/202609/18/2026

Actions
Task #1231: OLS Fiber Jig DesignNew03/05/202606/19/2026

Actions
Task #1232: OLS Fiber FabricationNew06/22/202608/31/2026

Actions
Task #1233: OLS Fiber AssemblingNew08/01/202608/31/2026

Actions
Task #1234: OLS Fiber PolishingNew09/01/202609/18/2026

Actions
Task #1257: OLS Fiber, Flange AssemblingNew09/21/202609/30/2026

Actions
Task #1259: Vacuum CheckNew12/01/202612/31/2026

Actions
Task #1261: MAPMT AssemblingNew01/01/202701/29/2027

Actions
Task #1263: Operation CheckNew02/01/202703/31/2027

Actions
Actions #1

Updated by Sho Nagao 3 months ago

  • Subject changed from PiSciFi to PiSciFi Construction
Actions #2

Updated by Sho Nagao 20 days ago

  • Subject changed from PiSciFi Construction to PiFi Construction
Actions

Also available in: Atom PDF