Project

General

Profile

2019 Run Plans and Run Sheets » History » Version 36

Garth Huber, 07/07/2021 02:31 PM

1 36 Garth Huber
h1. 2019 Run Plans and Run Sheets
2 1 Garth Huber
3
h2. Summer 2019 Run Period
4
5 19 Garth Huber
* Blank Run Sheets
6 9 Garth Huber
** New Configuration Sheet attachment:runsheet_pion.tgif.pdf
7
** Continuing Configuration Sheet attachment:runsheet2_pion.tgif.pdf
8
9 10 Garth Huber
* Run Plans
10
** Run Plan Spread Sheet attachment:pion_lowEkin_runplan.ods
11
** Run Plan attachment:runplan_lowQ2.pdf 
12
** SIMC Plots (low Q2 Fpi) attachment:tphi_lowQ2.pdf 
13 35 Garth Huber
** Scanned run plan (with shift worker and RC notes) attachment:run_plan.pdf
14 1 Garth Huber
15 10 Garth Huber
* Run List
16 34 Mireille Muhoza
** Runlist CSV file attachment:pion_runlist_summer19.csv
17 32 Mireille Muhoza
** Standard kinematics attachment:standard.kinematics
18 19 Garth Huber
19
* Run Sheets
20 20 Garth Huber
** 2.7 GeV Optics, Trigger, BCM (while waiting for ESR repair) attachment:optics_2p7gev.pdf
21 19 Garth Huber
** 2.7 GeV Run Sheets attachment:runsheets_2p7gev.pdf
22 29 Vijay Kumar
** 3.6 GeV Run Sheets attachment:runsheets_3p6gev.pdf
23 35 Garth Huber
** 4.5 GeV Run Sheets attachment:runsheets_4p5gev.pdf 
24 29 Vijay Kumar
25 21 Garth Huber
h2. Later high energy running
26
27
* Beam pipe requirements attachment:beampipe_req.pdf