03/25/2024
- 11:13 AM SBS DAQ GEp CDet Task #983 (New): Patch panel for TDC
- Need 12
03/18/2024
- 11:24 AM Task #981 (New): Install VETROC crate
- 11:23 AM Task #963: Installation of repeaters and cables for CDet in Hall A
- repeater installed
a few cables missing need to find and install - 11:21 AM Task #963 (In Progress): Installation of repeaters and cables for CDet in Hall A
- 11:22 AM SBS DAQ GEp CDet Task #948 (In Progress): Make VETROC adapters
03/04/2024
- 11:09 AM Task #964 (New): Put HV computer on network
- 11:09 AM Task #963 (Resolved): Installation of repeaters and cables for CDet in Hall A
02/26/2024
- 11:17 AM Task #954 (Closed): ECAL testing during GEn RP
- Test on module during GEN RP
will set SoLID VXS crate - need cosmics trigger form ECAL