03/25/2024

11:19 AM SBS-DAQ-GEn-RP Task #986 (New): Remote switch for HV
Alexandre Camsonne
11:18 AM SBS-DAQ-GEn-RP Task #985 (New): Helicity board test
Alexandre Camsonne
11:18 AM SBS-DAQ-GEn-RP Bug #984 (New): Scalers not working
Might be missing scaler not found Alexandre Camsonne
11:17 AM SBS-DAQ-GEn-RP Task #937: Active analyzer FADC and TDC cabling
What is status of FADC ? Alexandre Camsonne
11:13 AM SBS DAQ GEp CDet Task #983 (New): Patch panel for TDC
Need 12
Alexandre Camsonne

03/18/2024

11:24 AM SBS-DAQ-GEp Task #981 (New): Install VETROC crate
Alexandre Camsonne
11:23 AM SBS-DAQ-GEp Task #963: Installation of repeaters and cables for CDet in Hall A
repeater installed
a few cables missing need to find and install
Alexandre Camsonne
11:21 AM SBS-DAQ-GEp Task #963 (In Progress): Installation of repeaters and cables for CDet in Hall A
Alexandre Camsonne
11:22 AM SBS DAQ GEp CDet Task #948 (In Progress): Make VETROC adapters
Alexandre Camsonne
11:18 AM SBS-DAQ-GEn-RP Task #935 (Closed): HCAL trigger cabling to TS
Alexandre Camsonne
11:16 AM SBS-DAQ-GEn-RP Task #966 (Closed): Update prescale GUI to add new triggers
Alexandre Camsonne

03/15/2024

09:14 AM SBS-DAQ-GEn-RP Bug #973 (New): BBCAL noisy channels
Alexandre Camsonne

03/06/2024

10:43 AM SBS DAQ GEn RP GEMs Task #969 (New): Take cosmics BB GEMs
Alexandre Camsonne
10:35 AM SBS DAQ GEn RP GEMs Task #968 (New): Network cable clean up
Alexandre Camsonne
10:34 AM SBS DAQ GEn RP GEMs Task #967 (In Progress): order HV remote power switch
2 20A power switch
and 2 30 A power switch ordered
Alexandre Camsonne
 