h1. August 20th 2020 
 * Updates 
 ** VMM3 
 *** Ed talking with Jeff for packaging, might choose bigger packaging for FPGA for convenience for routing 
 *** BNL order is in so chip will be ordered soon 
 *** ATLAS testing setup could be borrowed or someone could go to CERN 
 *** Install VMM3 eval board with linux : managed to get data in ART mode 
 !https://redmine.jlab.org/attachments/download/1043/amp33.gif! 
 !https://redmine.jlab.org/attachments/download/1044/amp29.gif! 
 *** make adapter tp plug detector to test board with direct outputs 

 **MPD  
 *** Ben has access to clean room on week-end - was able to test at 1.25 Gbps seems stable - limit trigger to 2.7 kHz 6 samples 15 APV - need longer stability testing 
 *** need set up INFN clean room - will try today or tomorrow - for next week 
 *** few issues with MPD / CODA , Bryan will help , new procedure relies on new driver - need to know where config files are 

 *UMass test setup    ongoing 
 **Need connector to VTP, could ship one from Ben 

 **