December 15th 2025
  • ESB
    • ePAS approved, need ESC001
    • pulled power cables
    • connected VME crates, and check current draw around 3A
    • need to install TI, VTP in VME crates
    • Computer : DAQ and CODA setup on solidpc1, works with external and internal trigger - FADC working with pedestal - need to try with signal
    • still need setup VTP for GEM
  • GEM
    • All electronics is there : 7 or 8 MPDs, 20 APVs, need to check if Florian has his MPD, need back plane and adapters, can borrow 2 QSFP payload from Hall C
    • need 1 V1495
    • need make adapter for uRGroove
    • LV power supply for testing, check with Ellen if we can borrow the TDK supplies
    • Fan out box
    • Gas system : 1 can use
    • UVA detector late Januray at earliest
    • Florian MPD in PRAD setup - might need the APVs
    • VMM
      • Jeff has all 6 boards - will bring to DAQ lab for testing - Ching and Alex will learn with Harsh
      • LV : 12 V - Check MPDOD LV available - check monitoring - 14 to 15 V if 12 V needed - need check cable length
      • check Bill supply
      • VMM testing setup
      • VMM readout : single module -
      • plan copper transceivers
      • Ed implementation GBT
      • lpGBT implementation
      • need to cooling
        MRPC
        got link to NALU software - 8 channels
        vfTDC - checking to borrow NINO from SBS
        64 channels of SAMPIC - need to check for updated software
        *HV
      • MPOD, CAEN
        *Data rates and volume for Hanjie
        *Need to check with Hanjie for network setup
    • need to pull network cable f
      **Cerenkov
      • FADC based readout
      • Gas system - manual - need to check who takes care of t
      • might setup MAROC and SSP