July 7th 2022¶
- Updates VMM prototype
- 2 weeks for finishing setting up VMM
- 2 week for testing with cosmics with source
- Bryan looking into possible CODA option
- Discussion new preRD VMM testing
**upgrade 1 gigE to 10 gigE - test bandwidth throughput internally - might need implement parallel data path to take advantage to 10 gigE- CODA developement beam test : 4 chambers
- GBT developement with SAMPA with FELIX readout, so VMM GBT should work same
- DC regulator bPol 12 V - need design and move some components off the board
- lpGBT : need to reimplement lpGBT and VTRx+, GBT SCA
- new prototype would be required and new FELIX card :
- upgrading firmware to triple logic , rough possible cost estimate ~ 50 K$
- look for University with expertise