- Still need to do rotation test - so access to Hall today not clear
- lock-up Friday still
- Updates
- GEM
- reconnected cables in ESB : odd issue with APV ( one might be not well seated )
- Asar will help setup HV for GEM
- uRwell preparation with Jaydee
- issue with panasonic to hirose adapter : PR was rejected, trying to check if order can go through, not clear we will have it by May
- fall back solution use hirose VMM SRS system - need to find SRS system - can borrow Stony Brook one as last resort
- check what LV is needed ( SRS box might provide LV for VMM )
- need miniHDMI cables - Alex will check for miniHDMI to HDMI adapters
- Alex will set up cosmics trigger for GEM data taking and VMM
- will be able to try VMM with source and cosmics with Harsh
- check if MPOD works for LV
- Jaydeep will come April 5th
**HV
- can borrow one CAEN from Bill Henry
- will use CAEN HV crates from SBS
- ECal
- Michael preparing to set up ECAL modules
**Scintillators
- Todd dismounted every scintillators, all PMTs tested including the one from Bogdan
**DAQ check power available on rack -
- MRPC
- need cable adapter for discriminators
- need update firmware for waveform samplers
- GEM
- reconnected cables in ESB : odd issue with APV ( one might be not well seated )
- Asar will help setup HV for GEM
- uRwell preparation with Jaydee
- issue with panasonic to hirose adapter : PR was rejected, trying to check if order can go through, not clear we will have it by May
- fall back solution use hirose VMM SRS system - need to find SRS system - can borrow Stony Brook one as last resort
- check what LV is needed ( SRS box might provide LV for VMM )
- need miniHDMI cables - Alex will check for miniHDMI to HDMI adapters
- Alex will set up cosmics trigger for GEM data taking and VMM
- will be able to try VMM with source and cosmics with Harsh
- check if MPOD works for LV
- Jaydeep will come April 5th
**HV
- can borrow one CAEN from Bill Henry
- will use CAEN HV crates from SBS
- ECal
- Michael preparing to set up ECAL modules
**Scintillators - Todd dismounted every scintillators, all PMTs tested including the one from Bogdan
**DAQ check power available on rack -
- Michael preparing to set up ECAL modules
- MRPC
- need cable adapter for discriminators
- need update firmware for waveform samplers