Alexandre Camsonne, 03/05/2026 01:20 PM
| 1 | 1 | Alexandre Camsonne | h1. March 5th 2026 |
|---|---|---|---|
| 2 | |||
| 3 | * Updates |
||
| 4 | ** GEM |
||
| 5 | *** Log entry - tested all 2 slots backplanes - 4 from Dusting - 2 from Florian - 1 damaged one for Dustin - need to fix HDMI connector - issue with address I2C - seen ok with VTP - pedestal from all backplanes except broken |
||
| 6 | *** Jiwan will help setting the MPOD HV with slow - enough for testing - will need one more card for final setup - |
||
| 7 | *** help to run HV cables for GEM detectors - Friday or Monday |
||
| 8 | *** Gas system ready - will put a cap to keep it clean |
||
| 9 | *** Alex will set up cosmic trigger - most scintillator at WM - look for other scintillators - pre shower |
||
| 10 | |||
| 11 | |||
| 12 | **Cerenkov |
||
| 13 | ***mirror and PMT installed |
||
| 14 | ***N2 available |
||
| 15 | ***need to decide if we want to make it vertical - for cosmic |
||
| 16 | |||
| 17 | **Hall C counting house |
||
| 18 | *** DAQ computer setup |
||
| 19 | *** will meet tomorrow with network people |
||
| 20 | *** |