h1. Run Plan and Projected Event Rates
2
3 5 David Flay
The overview of beam energies as distributed across each shift are shown below 
4
5
!beam-energies.png!
6
7 6 David Flay
The electron rates, scaled down by the duty factor (1/(4.2*60)) is shown below. Note: Our first shifts on 1/14/21 are telling us that we have overestimated these rates my many orders of magnitude.  Current data rates are ~30 Hz (instantaneous).  
8 5 David Flay
9
!electron-rates.png!
10
11
The full run plan is posted in the attachment below.