1 1 Alexandre Camsonne
h1. April 30th 2026
2
3
* Updates
4
** GEM
5
*** DAQ running, found GEM latency for UVA
6
*** Jerry will come drill holes on Monday - need to clean up the table
7
*** 1 UVa, 1 uRWell
8 4 Alexandre Camsonne
*** check with Harsh for VMM
9 1 Alexandre Camsonne
** Hall C
10
*** 2 crates installed with CPU, VTP , SD and TI, but still need to put on network and boot
11
*** May 25th installation
12
** PMTs
13
*** ECal : 1 block - finishing test of last PMT and will install
14
*** scintillators are back : ready to install and test - 
15
*** preshower in WN still being worked
16
*** 2 independent config + 1 with both crates
17 5 Alexandre Camsonne
*** Alex will work on FADC trigger with Hayden  
18 4 Alexandre Camsonne
** Look for switch for Hall C from Hall A
19
** MRPC
20
*** starting to look at design of adapter