December 15th 2025 » History » Version 1

Alexandre Camsonne, 12/18/2025 01:38 PM

1 1 Alexandre Camsonne
h1. December 15th 2025
2
* ESB
3
** ePAS approved, need ESC001
4
** pulled power cables
5
** connected VME crates, and check current draw around 3A
6
** need to install TI, VTP in VME crates 
7
** Computer : DAQ and CODA setup on solidpc1, works with external and internal trigger - FADC working with pedestal - need to try with signal
8
** still need setup VTP for GEM 
9
* GEM
10
** All electronics is there : 7 or 8 MPDs, 20 APVs, need to check if Florian has his MPD, need back plane and adapters, can borrow 2 QSFP payload from Hall C
11
** need 1 V1495  
12
** need make adapter for uRGroove 
13
** LV power supply for testing, check with Ellen if we can borrow the TDK supplies
14
** Fan out box
15
** Gas system : 1 can use
16
** UVA detector late Januray at earliest
17
** Florian MPD in PRAD setup - might need the APVs
18
** VMM
19
*** Jeff has all 6 boards - will bring to DAQ lab for testing - Ching and Alex will learn with Harsh
20
*** LV : 12 V  - Check MPDOD LV available - check monitoring - 14 to 15 V if 12 V needed - need check cable length  
21
*** check Bill supply 
22
*** VMM testing setup 
23
*** VMM readout : single module - 
24
*** plan copper transceivers 
25
*** Ed implementation GBT
26
*** lpGBT implementation 
27
*** need to cooling 
28
**MRPC
29
***got link to NALU software - 8 channels 
30
***vfTDC - checking to borrow NINO from SBS
31
***64 channels of SAMPIC - need to check for updated software
32
**HV
33
*** MPOD, CAEN
34
**Data rates and volume for Hanjie
35
**Need to check with Hanjie for network setup 
36
** need to pull network cable f
37
**Cerenkov 
38
*** FADC based readout
39
*** Gas system - manual - need to check who takes care of t
40
*** might setup MAROC and SSP