| 1 | 1 | Alexandre Camsonne | h1. February 4th 2021 |
|---|---|---|---|
| 2 | |||
| 3 | *Updates |
||
| 4 | ** VMM |
||
| 5 | 4 | Alexandre Camsonne | *** gigabit ethernet working, data generated and sent through interface, next step hook up VMM evaluation board as data source - need phase adjustement between VMM and FPGA board - next step use pulse generator to feed VMM and use trigger to trigger FPGA board - finally plug GEM to board and use cosmic ray setup - setting up GEM in test lab so can look with source - |
| 6 | *** scaling from 12 to 128 using same gigabit ethernet for now |
||
| 7 | *** prototype board should be close to ready be end of February |
||
| 8 | 1 | Alexandre Camsonne | *** test board INDRA |
| 9 | 2 | Alexandre Camsonne | !https://redmine.jlab.org/attachments/download/1184/pdi_channel_run23.gif! |
| 10 | 3 | Alexandre Camsonne | !https://redmine.jlab.org/attachments/download/1185/lego_zoom_23.gif! |
| 11 | 1 | Alexandre Camsonne | *** |
| 12 | 4 | Alexandre Camsonne | ** |
| 13 | ** |