Alexandre Camsonne, 01/14/2021 03:34 PM

1 1 Alexandre Camsonne
h1. January 14th 2021
2
3 2 Alexandre Camsonne
* Updates
4 1 Alexandre Camsonne
** VMM
5 3 Alexandre Camsonne
*** Met with Ben, 1 Gbit ethernet working on developement board, when finished implemented will try run software ( linux, Ben could try to set up on Ed's computer )
6
***diagram test 
7
***VMM test with detector : try to separate the power, check ground connections of chamber to eval board. 
8
Separation helped with SAMPA
9
*** prototype board on going - 1 gbit on prototype and try 10 gigE after
10
*** parts from UVA - need to follow up - 
11
**APV
12
*** APV : 32 boards received - waiting for front panel prototype - should be ready by end of January
13
*** trying new firmware from Paolo, looks stable and running
14
** FADC : Ben working on VTP readout for FADC - still need at least 1 week - can see data transported to VTP from FADC firmware from Ed 
15
**UMass test stand
16
***testing with pulse close of calorimeter pulse
17
***deadtime in raw mode : 
18
***generating asymmetry with pulser
19
***NIM asymmetry box 
20
*Beam test FNAL
21
**support for ECAL beam test
22
** Ed and Ben provided information for electronics, review was ok, added kapton