January 15th 2026 » History » Revision 3

« Previous | Revision 3/4 (diff) | Next »
Alexandre Camsonne, 01/15/2026 01:07 PM


January 15th 2026
  • GEM
    • pulled extension cables to be surveyed
    • might not have enough HDMI - might need to open basket from SBS - need to count 20 or 30 meters cable
    • need to now cable length need
    • MPD crate booted, still need to check, need LV cables to power APV
    • need hostname for MPD crate and VTP , all on 196 subnet
    • VTP crate CPU booted solidgem2 , need to boot VTP
    • Talked with Harsh, just getting starting with VMM, will let us know when he starts looking at the readout
  • ESB
    • computer working for FADC readout, need to add VTP
    • SoLID HV MPOD crate in HKS area used by Jiwan, will move to SoLID : should have a few channel of PMTs, need to check if can use LV board for VMM
  • ARC detector
    • installed VXS crate with FADC for Zhiwen
    • readout list installed need to test with pulser and detector

Updated by Alexandre Camsonne 3 days ago · 3 revisions