h1. July 7th 2022
2
3
*Updates VMM prototype
4 2 Alexandre Camsonne
**2 weeks for finishing setting up VMM
5
**2 week for testing with cosmics with source
6
**Bryan looking into possible CODA option
7 1 Alexandre Camsonne
8
*Discussion new preRD VMM testing
9 2 Alexandre Camsonne
**CODA developement beam test
10
**GBT developement with SAMPA with FELIX readout, so VMM GBT should work same 
11
**DC regulator bPol  12 V - need design and move some components off the board  
12
**lpGBT : need to reimplement lpGBT and VTRx+, GBT SCA
13
**new prototype would be required and new FELIX card :  
14
**upgrading firmware to triple logic , rough possible cost estimate ~ 50 K$
15
**look for University with expertise