March 12th 2026 » History » Version 1

Alexandre Camsonne, 03/12/2026 01:19 PM

1 1 Alexandre Camsonne
h1. March 12th 2026
2
* Updates
3
** GEM
4
*** relocated crates to small racks for bunker, need floor map to set up cables. One more backplane broken, will try to fix but not clear it will work. Florian has a few spares. Alex will try to get more made
5
*** cables : 10 m HDMI cables labeled, enough for test beam. LV more than 10 m. SHV and BNC cables labeled ( 200 feet ) 
6
*** Jiwan put MPOD crate on Hall A EPICS, can control it now
7
*** Gas system ready : GEM flushing with N2, Ar/CO2 is ready to go
8
*** Alex will set external trigger for source and cosmics test
9
*** will test VMM next week
10
*** Things to go in Hall C : 2 VXS crates, cables, half rack will be brought later
11
12
** HV power
13
*** HV patch panels taken out from Hall A  
14
*** need 48 channels - need to check how many MPOD channels we have for PMT 
15
*** might need to add a Lecroy for PMTs
16
*** need to check rating for big HV cable 
17
18
** MRPC
19
*** can be put in support
20
*** flush with N2 if needed 
21
22
** Cerenkov
23
*** check gas system 
24
*** cosmics ?
25
*** Cerenkov RAM ?
26
27
** ECal
28
*** 2 modules 
29
30
31
** DAQ
32
*** CODA server set up, need to set up the ROCs
33
*** need to add network adapter
34
35
36
** Fibers
37
*** need to pull fibers from counting house to rack
38
***
39
40
** FADC ESB
41
*** need setup VTP readout for FADC