March 26th 2026 » History » Version 1

Alexandre Camsonne, 03/26/2026 01:38 PM

1 1 Alexandre Camsonne
h1. March 26th 2026
2
* Still need to do rotation test - so access to Hall today not clear
3
* lock-up Friday still
4
* Updates 
5
** GEM
6
*** reconnected cables in ESB : odd issue with APV ( one might be not well seated )
7
*** Asar will help setup HV for GEM
8
*** uRwell preparation with Jaydee
9
**** issue with panasonic to hirose adapter : PR was rejected, trying to check if order can go through, not clear we will have it by May
10
**** fall back solution use hirose VMM SRS system - need to find SRS system - can borrow Stony Brook one as last resort
11
**** check what LV is needed ( SRS box might provide LV for VMM )
12
**** need miniHDMI cables - Alex will check for miniHDMI to HDMI adapters
13
**** Alex will set up cosmics trigger for GEM data taking and VMM
14
**** will be able to try VMM with source and cosmics with Harsh
15
**** check if MPOD works for LV
16
**** Jaydeep will come April 5th
17
**HV
18
*** can borrow one CAEN from Bill Henry
19
*** will use CAEN HV crates from SBS
20
** ECal
21
*** Michael preparing to set up ECAL modules
22
**Scintillators
23
*** Todd dismounted every scintillators, all PMTs tested including the one from Bogdan
24
**DAQ check power available on rack - 
25
** MRPC
26
*** need cable adapter for discriminators
27
*** need update firmware for waveform samplers