Project

General

Profile

Gantt

Filters

Zoom in Zoom out « February | April »

months from Apply Clear

Task #663: Timing diagram
Task #664: Connect fibers
Task #665: VTP readout
Task #666: Cosmics
Task #658: SD recabling
Task #659: VETROC install
Task #660: VETROC readout
Task #655: Setup
Task #656: Training
Task #657: Test on GMn data
Task #653: EPICS scripts for 3 streams readout
Task #654: Stream Merger
Task #661: Fibers for MPD patch
Task #662: Add SBS VTP

Status

New
New
New
New
New
New
New
New
New
New
New
New
New
New

Priority

Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal

Updated

06/01/2022 06:33 AM
06/01/2022 06:35 AM
06/01/2022 06:36 AM
06/01/2022 06:36 AM
06/01/2022 06:10 AM
06/01/2022 06:14 AM
06/01/2022 06:14 AM
06/01/2022 06:05 AM
06/01/2022 06:05 AM
06/01/2022 06:05 AM
06/01/2022 05:59 AM
06/01/2022 05:59 AM
06/01/2022 06:31 AM
06/01/2022 06:31 AM
 
 
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
SBS-GEn-GEM
New 0%
New 0%
 

Also available in: PDF PNG