Task #1047: Look up tables for selective readout
Task #1048: Algorithm for GEM region of interest
Task #1050: Improve error handling APV and MPD
Task #1052: LV improvements : spread more ?
Task #1067: suspicious MPD testing
Bug #1068: swap optical receivers
Task #1069: Common mode histogramming method online
Task #1081: Modify readout list to reload firmware at prestart
Bug #1082: New Module to be installed

Status

In Progress
In Progress
Resolved
New
In Progress
Resolved
In Progress
In Progress
Resolved

Priority

Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
High

Updated

03/07/2025 10:07 AM
03/07/2025 10:07 AM
03/07/2025 10:07 AM
02/28/2025 11:25 AM
09/05/2024 02:35 PM
03/14/2025 11:40 AM
02/28/2025 11:29 AM
03/14/2025 11:39 AM
03/07/2025 11:20 AM
 
 
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
SBS DAQ GEp GEMS
 

Also available in: PDF PNG